The
design of the Ju 87 had begun in 1933 as part of the Sturzbomber-Programm.
The Ju 87 was to be powered by the British Rolls-Royce Kestrel engine. Ten
engines were ordered by Junkers on 19 April 1934 for £ 20,514, two shillings
and sixpence.The first Ju 87 prototype was built by AB Flygindustri (sv) in Sweden and secretly brought to Germany in late 1934. It
was to have been completed in April 1935, but, due to the inadequate strength
of the airframe, construction was not completed until October 1935.
However,
the mostly complete Ju 87 V1 W.Nr.c 4921 (less non-essential
parts) took off for its maiden flight on 17 September 1935. The aircraft
originally did not carry any registration, but later was given the registration
D-UBYR.[8] The flight report, by Hauptmann Willy Neuenhofen,
stated the only problem was with the small radiator, which caused the power
plant to overheatThe Ju 87 V1, powered by a Rolls-Royce Kestrel V12 cylinder
liquid-cooled engine, and with a twin tail, crashed on 24 January 1936 at
Kleutsch near Dresden, killing Junkers' chief test pilot, Willy Neuenhofen, and
his engineer, Heinrich Kreft. The square twin fins and rudders
proved too weak; they collapsed and the aircraft crashed after it entered an
inverted spin during the testing of the terminal dynamic pressure in a dive.
The crash prompted a change to a single vertical stabiliser tail design. To
withstand strong forces during a dive, heavy plating was fitted, along with
brackets riveted to the frame and longeron, to the fuselage. Other early
additions included the installation of hydraulic dive brakes that were fitted
under the leading edge and could rotate 90°.
The most notable feature of the
Stuka was its inverted gull wings, as shown in this photograph. Also visible
are the two separate sliding "hoods" of the canopy.
The
RLM was still not interested in the Ju 87 and was not impressed that it relied
on a British engine. In late 1935, Junkers suggested fitting a DB 600 in-line
engine, with the final variant to be equipped with the Jumo 210. This was
accepted by the RLM as an interim solution. The reworking of the design began
on 1 January 1936. The test flight could not be carried out for over two months
due to a lack of adequate aircraft. The 24 January crash had already destroyed
one machine.
The
second prototype was also beset by design problems. It had its twin stabilizers
removed and a single tail fin installed due to fears over stability. Due to a
shortage of power plants, instead of a DB 600, a BMW "Hornet" engine
was fitted. All these delays set back testing until 25 February 1936.
By March 1936, the second prototype, the V2, was finally fitted with the Jumo
210Aa power plant, which a year later was replaced by a Jumo 210 G (W.Nr.
19310). Although the testing went well, and the pilot, Flight Captain
Hesselbach, praised its performance, Wolfram von Richthofen told the Junkers
representative and Construction Office chief engineer Ernst Zindel that the Ju
87 stood little chance of becoming the Luftwaffe's main dive bomber, as it was
underpowered in his opinion. On 9 June 1936, the RLM ordered cessation of
development in favour of the Heinkel He 118, a rival design. Udet cancelled the
order the next day, and development continued.
No comments:
Post a Comment